Comment
  
  
Additional Comments
  
  
  
Board Letter064697941.pdf
  
Status report for the Inland Feeder Program for activities through August 2009MWD/Board of Directors
9-1Board of Directors^Engineering and Operations Committee
200910/13/200910 - Oct
Board Letter064697943.pdf
  
Report on Carlsbad Seawater Desalination Project with San Diego County Water Authority and its local retail agenciesMWD/Board of Directors
9-2Board of Directors^Water Planning and Stewardship Committee
200910/13/200910 - Oct
Board Letter064697925.pdf
  
Cost of Service Review UpdateMWD/Board of Directors
7aBusiness and Finance Committee
200910/12/200910 - Oct
Board Letter064697929.pdf
  
Appropriate $470,000 and authorize preliminary design of post-filtration chlorination capacity increase at the Diemer and Weymouth plantsMWD/Board of Directors
7-2Board of Directors^Engineering and Operations Committee
200910/13/200910 - Oct
Board Letter064697933.pdf
  
Appropriate $280,000; and authorize a seismic study to evaluate the CRA electrical switch housesMWD/Board of Directors
7-4Board of Directors^Engineering and Operations Committee
200910/13/200910 - Oct
Board Letter064697927.pdf
  
Appropriate $140,000 and authorize final design of the Lower Feeder Erosion Protection ProjectMWD/Board of Directors
7-1Board of Directors^Engineering and Operations Committee
200910/13/200910 - Oct
Board Letter064697937.pdf
  
Appropriate $12.1 million; and award $9,085,000 contract to Sukut Construction, Inc., for construction of the Diemer North Access RoadMWD/Executive Secretary
8-1Board of Directors^Engineering and Operations Committee
200910/13/200910 - Oct
Board Letter064697931.pdf
  
Appropriate $1.21 million; and award $798,006 construction contract to Corrpro Companies, Inc. to install a cathodic protection system on the north reach of the Middle FeederMWD/Board of Directors
7-3Board of Directors^Engineering and Operations Committee
200910/13/200910 - Oct
Board Letter064697935.pdf
  
Appropriate $1.19 million; and authorize preliminary design of lining repairs for the Etiwanda PipelineMWD/Board of Directors
7-5Board of Directors^Engineering and Operations Committee
200910/13/200910 - Oct
Board Letter064697939.pdf
  
Adopt resolution to approve notice of potential discontinuance of interim agricultural service of surplus water from October 1, 2010 through September 30, 2011MWD/Board of Directors
8-2Board of Directors^Water Planning and Stewardship Committee
200910/13/200910 - Oct